First Marine Surveyors Company

KOMSA


Towage&MWS
ENGINEERING
Review of Drawing of PJT Cargo

KOMSA has many experiences of MWS & Towage surveys on big projective cargoes, i.e, RTGC, RMQC, Evaporator, CSU, Floating Crane & Etc. reviewing engineer drawing with our engineering program.

Through the engineering meeting, we advise the concerned the safety sea-fastening and rolling, pitching, heaving degree and sufficient lashing for sea-transportation.

Reviews of Main Engineering
  • Towing force calculation
  • IMO Lashing calculation
  • Motion of sea transportation
  • Tugboat bollard pull calculation
  • Sea-fastening force calculation
  • Wind force calculation
  • Stability calculation
  • Ped-eye strength calculation
  • Welded strength calculation
  • Ship’s Mooring force calculation
  • Lashing wire strength calculation
  • Roll on, Roll off force calculation

Towing force calculation
IMO lashing calculation
Tugboat bollard pull calculation
Motion lashing calculation
Sea-fastening force calculation
Wind force calculation
Stability calculation
Ped-eye strength calculation
Welded strength calculation
Ship’s Mooring force calculation
Lashing wire strength calculation
Roll on, Roll off force calculation
Towage/Warranty
1700 Ton of Port Crane-Loading Process
  • - Wire Pulling by Deck Winch
  • - Survey Points : Welding status to Winch, Sea-Swell Balance between Jetty and Barge deck, Bridge Beam.

4500 Ton of Evaporator-Loading Process
  • - Loading on SPMT by Roll-On, Roll-Off
  • - Need Operator’s skill, ballasting, good weather.
Warranty Survey
200 Tons of Yard Crane-Loading Process
  • - Loading by Skidding system
  • - Equipping the rail and winch.
  • - Need good weather, vessel’s ballasting and sufficient ramp.

1500 Tons of RMQC-Unloading Process
  • - Loading by Skidding system
  • - Equipping the rail and winch.
  • - Need good weather, vessel’s ballasting and sufficient ramp.

1500 Tons of RMQC-Loading Process
  • - Equipped Loading beam to main body
  • - Loading by SPMT.
  • - Need full welding, full lashing/securing, ballasting.

6000 Tons of Floating Crane, 3000 tons Barge, Tugboat-Loading Process
  • - Semi submerged vessel
  • - Need skillful engineer, full supporting, wire-fastening.
MAIN EXPERIENCES(MWS)
January 2012 ~ June 2013 : 8 Evaporators
  • - View of Loading on Barge at Changwon, Korea
  • - View of Arriving at RAK, Saudi Arabiya

March 2012 : 6 RMQC
  • - View of Loading at Changwon, Korea
  • - View of Arriving at Kuwait

July 2011 : 75 ea of RTGC
  • - View of Loading at Lampung, Vietnam
  • - View of Arriving at PSA, Singapore

March 2009 : GS Salalah Methanol Project (Oman)
  • - View of Loading
  • - View of Completion of Loading

March 2012 : Toyo Aljubail PLT
  • - View of Loading
  • - View of Completion of Loading

Towing/Warranty Survey
2015 : Module on Self propeller barge and Cable

2015 : Jacket and 8000 ton tera block